Area is boarded just want a time needed idea when looking at quotes.
Thank you!
4 days 1 coat per day plus sanding
Hi Paul. A room with no bulkheads and bump outs should take 3-4 days to tape/mud and sand, walls and ceiling.
Steve.
Hi,
Properly finished. Five to six days.
Hi, everyone's quotes here are correct. Keep in mind, however, that actual application time for each coat is only a few hours per day. It depends on the amount of inside corners, how well the drywall was installed, and the height of the ceilings. A good muddier is quicker and can do it in less coats!
For a space this size, you're looking at 3-4 days. The actual coats won't take days. It's the drying time and sanding.