I have a space in my mississauga home basement which is approx 10' x 35'. My plan is to allocate half (or two thirds) as a home gym and the rest as a kids play area. The whole space would have gym/rubber floors, perhaps coloured etc. For the play area portion. Full wall Mirrors would be up in the gym, punching bag installed, weights, mats, etc, among other items. Playroom pretty straight forward. Perhaps french door splitting the spaces and tvs wired/mounted as needed.
Pretty straight forward. Quotes, interest welcome.
Basement Kitchen
- L-shape 15 linear feet
- Electrical wiring and plumbing line for sink completed. Drywall and flooring completed recently
- MDF cabinets. Corner shelf easy reach cabinets. Soft stop
- 30 inch top cabinets
Basement Staircase
- Total 12 steps (2 + 10) from main level to basement level
- Oak staircase with white risers
- spindles/picket hand railing
Main level kitchen
- top cabinet (stained maple) above OTR microwave to be resized to lower the microwave. Currently too high for practical daily use
- Valance for under cabinet lighting
Our basement storage area flooded due to all this rain and the insurance company has denied our claim. We have water coming in from our dryer vent and draining into the storage area as well as a suspected crack in the foundation as water is also seeping through the back wall. The storage area was finished (fooring, drywall and ceiling) as it was used as a kids playroom years ago. Before the claim was denied the insurance had a demo crew in so half the ceiling is torn out as well as some carpeting is cut out from the family room.
We are looking to
-have basement emptied
-get the dryer vent sealed and relocated,
-ceiling put back together,
-crack in the foundation sealed, with new drywall over top
-then new vinyl/laminate laid throughout storage, laundry and bathroom as well as new carpet in family room.
-and finally everything put back in its proper place in the basement and all trash hauled away
Any further questions please dont hesistate to e-mail, we just really need our basement put back together asap!
The semi detached house in Mississauga is about 45 years old. When I bought the property the basement was already done. Most probably it is not legal. I want to have three bedrooms instead of two bedrooms and want to make it legal. I know the steps to make it legal and get it done by contractors/pros on this site.
Should I hire an architect?
Turning an existing finished basement family room (approx 22 ft x 13 ft) into a basement pad.
DEMOLITION and REMOVAL
(could be done by contractor with/without assistance of owner)
- Remove existing ceiling (stucco drywall, bulheads around heating ducts, pot lights)
- Remove existing brick fireplace hearth and fake chimney
- Remove existing bar (approx 8ft long, wood, brick cladding)
- Remove existing carpet (to be used in another room)
- Remove existing floor tile
RENOVATION
- Install new wall with door to block new room off (approx 8 ft)
- Install new electrical (outlets, pot lights, ceiling fan)
- Install new floor tile
- Install new closet with mirror sliding door (owner to install
- Install new Ikea kitchen cabinets (approx 14ft length in total, including sink/faucet, microwave shelf, under counter fridge opening, NO stove)
- Install new ceiling (drywall, NO stucco)
- Install new carpet
- Paint (optionally done by owner)
Hello Contractors,
I own a small music studio in the basement of my home in Mississauga. The basement is finished already and includes a room, hallway, washroom and living area. The room is where the music studio is.
I would like to remodel the basement and enlarge the music studio from the small room right into the living area so that the studio become the living area.
This is a two step project for me and you will most likely be involved in the 1st step, unless you have specific music studio installation and retrofitting experience.
Step 1: enlarging studio and remodeling living area with special studio materials (soundproofing) and breaking down of a few walls along the way.
I invite you to come see what I had in mind so we can discuss a possible quote range.
Thank you!
Dany
We finished this basement 5 years ago, but due to a water leak, there was damage to the floor.
The leak has been repaired and we're now looking to have things put back in place .... sub-floor (Dri-core), laminate, a bit of drywall, and re-attaching the door and service door covering the water meter ...
We can source the laminate ... area is approx. 8*10 (?)
Age of house: ~40 years.
Project: take down inner basement walls, waterproof* and repair as needed, rebuild inner walls.
Current walls: stucco and wood panelling
New walls: Plain with trim and paint
*waterproofing (on exterior wall only, ~25 ft) is the responsibility of my condominium corporation - not clear at this time whether they will want to hire their own contractor. Home has had multiple leaks in the past few years, all repaired from outside; now considering inside sealing.
site conditions: currently dry, finished basement, carpet flooring
total wall length ~ 70 ft, height ~ 6.7 ft
I have a finished basement in a Semi-detached home and would like to convert it to a legal secondary unit with a new washroom in cellar space, a walk-out secondary exit, and a small kitchen /cooking area. I may also consider renovating the main kitchen and creating a new interior garage door into the house.
I would need a licensed and insured company that is willing to provide proof of StatDec, WSIB and liability insurance.
i have partially finish basement(,from previous owners).it was do it yourself job i guess , now i want it to be finish so i can use it.i just want a big space so my kids can have enough place to play may be i will ask for some partition or room to make for storage. this is 15 year old twon house ( approx 1700 sq ft).
I would like to do my basement reno in stages approx. 1000 sqft with 8ft ceiling;
- The basement will have one washroom, one bedroom with walk-in closet, and main living area with designated bar area
-Have the basement framed
-washer and dryer moved near the furnace and drain area
- have concrete leveled
- plumbing includes shower/tub installation
- all electrical with pot lights in the living room and bar area
- have stair case finished
1. Additional Bathroom (rough-in, framing, electrical is completed)
2. Re-positioning of furnace and water heater (approx 4 ft from original location)
3. Mini kitchen counter (approx 8 ft long, with sink and vent fan only)
4. Bedroom (8x12 ft)
5. Laminate flooring (approx 700 sq ft)
gut and rebuild basement and sub basement for a 4 level back split. change into master bedroom, two bedrooms, 4 piece bathroom, play room laundry and family room.
excavate front and side patio and regrade and water proof exterior walls.
re wire basement and upgrade current fuse box to breaker system
replace windows (4 -6)
preferably done by septemer 2012
15 years approx
1000sq ft
open concept kitchen
full bathroom
1 bedroom
combined living space and dining area
need:
paint
replace carpet
bathroom renovated and repaired
kichetn renovated and repaired
doors and window touched up and painted
entrance to the basement painted and doors painted
Hello,
My boyfriend and I are moving in to our home Feb 11th 2011, the basement in the house is finished with a half bathroom, and we are looking to do some renovations to the space. We are currently requesting quotes at this time. Not sure what you require to provide us with one. Below are some details
Looking to add a shower
redo ceiling as it is currently dropped ceiling.
There are wood paneling that we would like to remove and just have reg dry wall
carpet removed on stairs as well as basement floor replace with laminate.
BSMT dimensions are 20.41x 15.49
We can provide the supplies as well.
House is in Mississauga it is 28 years old.
Thanks in advance for your time.
We have an unfinished basement that needs to be built from scratch. We would like to have separate quotes for each of the steps indicated below:
1) Subfloor
2) Framing
3) Drywall
4) Painting
Please provide material and labour quote, separately, for each of the above steps. I can email you a PDF file with details on rooms and sizes. At this point we are looking to get started and later on we will ask for quotes for washroom and kitchenette.
Thank you.
NOTE: GIF file added with details.
BASEMENT RENOVATION
Looking for a Contractor interested in basement renovations within the Port Credit, Mississauga Area. Able to provide cost saving solutions and work within budget. Must be reputable and provide recent project references. Family will be living at home during the renovation period.
Description: Original home was built in the 50's (cottage style). Then in the 80"s the previous owner torn down the structure to build a 3300 sqft 2-storey home. Now recently in 2010, we bought the home which needed to be upgrade throughout the home. Most of the renovations were done to the first and second story of the house and now we plan to complete the basement this year. The basement will be designed for Theatre/Entertainment room, spare bedroom, storage closets, and new bath 3pc bathroom with sauna. Flooring to be combination of tile and laminate wood flooring. Work will include removal of foundation wall (built from the original 50's cottage) to expand room size. This will require new footings, column relocations, and new structural support for first floor. House has access to basement from mudroom which is connected to the garage and also from main hallway.
Scope of Work:
- hoarding basement from main upstairs.
- demolition of existing tile floor, drywall, foundation walls.
- relocate structural supports, insert new beams.
- rework air ducts and provide return air feed for basement.
- framing, drywall, insulate exterior walls (spray foam).
- electrical wiring, pot lights, new outlets, etc.
- plumbing for new bathroom and build sauna.
- install new basement windows.
- Trims & doors
- prime and paint all walls.
- install tile and laminate wood flooring on sub-floor.
- plus more.
Option:
- build 8ft x 19ft loft in Garage for additional storage.
Schedule: Start May -June 2013 (due to heating)
I have a partially finished basement that I would like to turn into a rental unit but leave some space for me that can be used for storage and fitness room. The house is roughly 2300sqft. There is only one access Point into the basement through the house. I would like to put stairs in from the garage, new windows, 1 or 2 bedrooms with kitchen, bathroom and sitting area. The electrical is very old. My gut says we need to take it all out and start from scratch. The basement had ceramics but covered the floor with laminate. The area is open concept but previous owner put in a bedroom that we use as an office. The space is not used properly. We may or may not rent it out but I would like the choice. My oldest is starting university so we may move him into the basement.
Hi, we have a 2 year old house and want to finsh the basement.
I'd like to use spray foam as to replace current insulation and soundproof the basement ceiling. 3 piece bathroom with shower.
We plan to have 2 storage rooms and one office. Potlights throughout and pre-wired for entertainment system. Looking for advice on replacing current staircase to Oak. Looking for professional advise on the right layout. I can be reached anytime on my cell phone .
Thank you for your time.
Don
Middle Unit Town Home.
I'd like to finish the basement completely. It is currently unfinished from A-Z (with the exception of 50% of insulation complete).
About 700 sq. ft.
Wish List: Dry wall walls and ceiling. Pot lighting. Move plumbling for washer and dryer about 5ft to adjacent wall. Subfloor and floating floors. Box in furnace (leave access). Wire for tv, speakers.
**Access to basement is around narrow winding staircase. Will most likely involve the need to cut drywall sheets in half in order to bring them downstairs.
Post your project and let top-rated pros compete to get your business. Compare bids, read real customer reviews and hire the best contractor the first time.