The house we just bought is about 75-year old. Right now we are converting the house into a legal duplex: Main+basement is one unit and upper floor is the 2nd unit. Contractor must do the job according to the city regulation for duplex instead of single family home i.e. thickness of drywall and door, smoke detector and CO detectors, etc.
So far new concrete is already poured and electrical wiring is done. Wood studs have been set up along the walls.
What needs to be finished: Drywall, Ceiling with spot lights, Ceramic floor, A new 4-pc bathroom inclu. plumbing; Partition wall; Put new window and block an old one; Change doors; No electrican needed, owner has his own electrician to work with.
New basement floor, need the framing completed to complete electrical and plumbing. After that will finish celing per Toronto code with Z channels and then dry wall the whole thing. Need done soonish. Is 500 Square feet with easy location to load drywall through large window covered by board.
Thx
Jon
Quotes requested for finishing a basement which is a total size of 1500 sq ft & turning it into 2 apartments.
Each apartment will have:
- 1 bedroom each
- a separate kitchen,
- a separate living room
- a separate 3 pc bathroom
Please provide a ballpark estimate for materials & labour for:
- Framing (including strengthening framing for existing laundry room)
- Drywall
- Porcelain tiling (throughout entire basement)
- Electrical (including rerouting). Pot lights please
- Insulation
- Plumbing
- Bathroom and kitchen fixtures
- Cutting into one basement wall to create an extra window
- Painting
- Anything other major things I've forgotten to think of.
Much thanks.
Hi
I am looking to hire a contractor to complete my basement.
The property is 120 years old, Rowhouse in downtown Toronto. Near king and bathurst area.
The basement is waterproofed already.
The requirement for the basement is the following,
- a single bedroom,
- a bathroom (2 or 3 piece depending on design).
We are looking to get the work started ASAP with the right contractor.
Verification of insurance coverage and bonding will be required. A total of 3 reference of current work completed in the last 6-8 months.
All estimates will be requried in writing along with draft layout work. Also confirming with a payment schedule upfront.
Thank you for your interest.
Looking for reliable contractor to finish work in basement.
Need the following completed:
Slate tile floor installation for powder room and hallway 60 sf
Install laminate floor in gym area 140 sf
Minor sand, full prime, and paint existing walls and ceilings. approx 800 sf
Carpet on stairs and install hand rail
Carpet tile in lunge area
Install all plumbing fixtures - toilet, powder room, and wet bar sink (rough ins installed)
Hang powder room accessories.
We would like to finish our basement. Two years ago we completed a home addition, unfortunately we were unable to refinish the basement at that time. The total square footage of the basement is approximately 1100 square feet. The addition component of that is around 500 square feet. The exterior walls are all insulated and ducting in the house was completely redone with the addition. There is a sump pump in the addition and the ceiling is 8 feet in the addition and around 7 feetin the old section. In the new section we would like to simply divide the space into an office area and a family rec. space.
In the old section we would like to put in a 2 piece powder room, guest bedroom, basic shower, and storage.
We would appreciate quotes on the total project as well as just finishing the addition section. We have some initial drawings if that would be helpful. The older section currently houses the mechanical room and laundry, both of which are adequate.
We would like to receive quotes as soon as possible and are busy clearing out the basement to ready it for work as soon as possible. However, we do have flexibility around dates and can be accomodating around start times.
Looking forward to hearing from interested bidders as soon as possible.
We are looking for a contractor to finish our basement in the Beaches area of Toronto. The house was built in the 1920s. The area of the basement is about 750 square feet and likely needs to have the concrete floor dug out for enough height. There is an existing two piece bathroom, a laundry room, and cold room and we would like to renovate to include a separate bedroom, a three piece bathroom and laundry room and family room with storage space.
I'm looking for someone to finish my basement. It's approx. 20 ft. x 50 ft.. We'd like to add insulation (currently none) and a bathroom and a kitchen. We currently only have a laundry sink in the basement. As for lighting, we'd like to have pot lights and a few wall sconces. Please quote the job as follows (we may like to finish some of it ourselves):
1. Framing
2. drywall
3. plumbing (rough in and finish)
4. electrical
5. Painting
6. Trim
7. Laminate flooring
Jonathan
House is 10 years old, I would like to finish the basement. It only has the insulation done.
I would like to build a bathroom down there with a stand up shower, i would
Like to have built in book cases on one of the walls. So I need pluming done for bathroom and electrical done as well for some pot lighting.
We have a 1200 sq feet basement, and would like to finish it as a two bedroom appartment. Looking for highly skilled and inovative contractors for completing this job.
Being on time, and on budget is key. Contractor must be lisenced and use insured, licensed sub-contractors.
Please contact for further information
We'd like someone who can provide several reference, and is been in this business for at least 10 years.
Hi,
We are looking to have:
- our roughly 550 sqft basement finished: with a simple bathroom + kitchen; basement does not need digging; plumbing is available
- a second floor balcony installed, and the second floor window replaced by a door with access to the balcony: for a rough sense of the type of balcony we are looking for + pics of the (pretty terrible) current situation seeclick here a first floor deck slightly bigger than the balcony (and directly underneath it) installed (our AC unit in the backyard will have to be moved)
Looking forward to hearing if you can help us with this project.
Our basement has never been finished. It's around 800 sq.feet. House was built in 2006. Need to have a 1 bedroom apt. with small kitchen, washroom and laundry room. Project should be completed possibly in August.
Good quality material, nothing over the top. Budget is around 25000.
We would like to see previous jobs done by Contractor + references from customers.
Gibril
We have a 100 year old house in Riverdale, with 2 projects:
1. Finishing the basement, plus bathroom. Basement is completely unfinished, except for a previous bathroom, which has been removed (plumbing probably intact). Total approx. 550 sq ft. Looking for someone with experience with old houses.
2. Increasing usable space on third floor by building 2 dormers. Each dormer would be approximately 8 ft. wide, one with a window.
Thanks!
We are planning on partially finishing our basement this fall (approx 315sqft, 90yr old house), which would include insulating, pot lights, electrical outlets, drywall, and create storage closet. We need a tv/play space as well as a storage area. The walls are currently covered in panelling with 2x2" framing and the ceiling is open.
We live in Toronto around Danforth and Coxwell/Woodbine, in a semi. Our basement has a wide half-height door entrance from the backyard, as well as regular entrance from upstairs (but very narrow). The basement is dry and we don't need to waterproof from the outside. The height is acceptable and we don't want to dig down. Also, we'd like to do the demo ourselves, but need you to take care of garbage removal. The flooring would be done by us as well. If you need more info please contact me.
Our house is approximately 90 years old. It is on the end of a row of six and has three windows (newer) on the north side. The basement has never been finished and it sits on the water table. The mortar on the walls is crumbling, therefore a sophisticated waterproof membrane is needed, along with interior weeping tiles. It also needs to be lowered (by hand--not by jackhammer),waterproofed, and then refinished. There are two smaller rooms--one at the front and one at the back. The one at the front will be storage and also the area for the furnace and water heater, etc. The rear room will become a second washroom and laundry combo.
For finishing, we would like some shelving to be built into the walls, pot lights in the ceiling, and floor heating in the bathroom/laundry.
We have an architecht who has drawn up blueprints and is obtaining the appropriate permits.
All contractors will be asked to provide licensees and references of their work.
We are moving in with my Mom in her basement. It needs to be totally gutted and then renovated. We need drywall, paint, electrical and a bathroom done.
The house is about 1500 square feet and has paneling and a bar now which all needs to come out.
I would like a quote online please and then we could arrange a site visit.
Thanks
We had to rip out the basement apartment kitchen and wall (about 20 feet of wall) in order to install an interior weeping tile system to prevent an ongoing seepage problem. Now that's fixed (not a drop after several big rainstorms), we want to put the kitchen back in.
We are looking for about 12-14 feet of kitchen (simple cabinetry, single sink, electric stove, countertop). Also required: replacing the doorframe and door in the separate entrance to the apartment, as well as possibly replacing one window (in the existing location and size). Possibly include installation of stackable washer/dryer.
Finally, we are also considering the possibility of upgrading to 200 amp service, and re-wiring the house before (or while) we get the kitchen done in the basement.
I am heading out of town for 3 weeks starting in 1 week, so would like to see if I can book someone before I leave, for work to begin after my return (October 3).
Would like to schedule work to begin in mid-October if possible.
Found some pooled water in the basement following a recent have rainfall. Water was only in one corner of the basement. I need someone to identify the source of the leak and make any necessary repairs. Basement is partially finished - the leak is around the part that is finished.
Home is 100 year old downtown Toronto home. Scope of the project may include demolition of the kitchen area where the leak is located, possible plumbing work or foundation work, depending on the source of the leak.
100 year old beaches area home (this means sandy soil type)
Six feet current headroom needs to be increased. If bench technique is appropriate, 18 more inches of clearance would be great. If underpinning, may as well go for eight feet of headroom.
Will rough in drains for future bathroom, furnace to be removed for future replacement.
Owner is tradesman & has resources and want to spend budget on bones of project and contribute personally. This means I might be able to do drains or some excavation/removal myself. This dependent on agreement with contractor to spend more time on skilled aspects of job. Intermittent pours etc. may allow owner to prepare areas ahead of and after critical pours.
As tradesman can deal with others in professional manner and appreciate viewpoints or technical aspects.
A SUBCONTRINACTOR IS REQUIRED TO DO AN UNDERPINNING JOB ON 109 L FT OF PERIMETRAL WALL. LOWER THE FOUNDATION 18" EXCAVATE FLOOR UP TO 18" AND THEN REPOUR GRAVEL AND CONCETE FLOOR 1' LOWER THAN EXISTING. aCCESS AVAILABLE ON SIDE FRONT WINDOW. PLEASE QUOTE BASED ON THE LINEAR AND SQUARE FOOTAGE PROVIDED. BASED ON YOUR PRELIMINARY QUOTE WE WILL INTERVIEW. PICTURES WILL BE PROVIDED LATTER